Southeast Water Purification Plant

Location: Houston, TX
Project Type: New/Expansion
Owner:
City of Houston
Nat Iyer 832 395-2367
Engineer:
Camp Dresser & McKee
Brent Nicholas, P.E. 713 423-7300
General Contractor:
Pepper Lawson-Renda, LLC
Bart Adams 713 532-0174

Project Scope

80 million gallon per day water plant expansion. The largest single utility infrastructure project ever built in Houston. Subcontractor to Pepper Lawson-Renda, LLC for Electrical, Instrumentation, and Security including:Temporary power; above-ground and below-ground duct banks; Switchgear expansions to the existing 138Kv Substation 12.4Kv switchgear to feed the Treatment Module 2 Addition and 7.2Kv Switchgear to feed the High Service Pump Station Expansion; Process Instrumentation and Controls; Networking and UPS; Fiber Optic Data Network for new/existing plant SCADA Communication; Security MUX panels for CCTV; Security Access; Fire Alarm System; Standby Diesel Engine Generators.

Project Details

Original Construction Cost
$34,118,934
Date of Notice to Proceed
06/08
Substantial Completion
02/12
Final Payment Dates
04/12
Project Superintendent
Tim Adam
Final Construction Cost
$34,972,475
Type of Construction
New/Expansion
Actual Substantial Completion
03/12
Project Managers
Gary Divin
Jack Levy, Stacy Jordon
General Contractor
Pepper Lawson-Renda, LLC
Bart Adams 713 532-0174
Length of Relationship with Owner
30 years