White Oak Bayou Drainage and Detention Facilities

Location: Houston, TX
Project Type: Landscape & Irrigation
Owner & Landscape Architect::
Mike Duane, Project Manager - 409 740--4266
Landscape Architect Houston Division - Dana Cote 713-802-5569

Project Scope

Boyer began construction of a new landscape development on detention ponds as a subcontractor to Balfour Beatty Infrastructure Inc. in October 2013. The project limits consists of approximately 22 acres along White Oak Bayou, north of Interstate 10, west of Yale to east of Shepard. Landscape installation included 5,500 large trees and shrubs with a full automatic irrigation system. Boyer provided irrigation and maintenance services for two years.

Project Details

Original Construction Cost:
$523,143
Final Construction Cost:
$523,143
Date of Notice to Proceed:
10/2013
Type of Construction:
Landscape & Irrigation
Original Substantial Completion:
02/2014
Actual Substantial Completion:
02/2014
Final Completion post Maintenance
02/2016
Project Manager:
Sid Morse
MEP subcontractors:
Boyer Self Performed
Length of Relationship with Owner:
15 years