TXDOT Beltway 8 West Landscape Beautification Project, I-10 to Hollister

Location: Houston, TX
Project Type: Landscape
Owner & Landscape Architect::
Landscape Architect Houston Division
Dana Cote 713 802-5569

Project Scope

21.348 miles of Landscape & Scenic Enhancement Work In October 2011, Boyer, Inc. began construction of a new landscape development on Sam Houston Toll Way. The project limits began on Beltway 8 West, north of Interstate 10 to Hollister. The twenty-one mile landscape construction project included the installation of 70,000 trees and shrubs along both sides of the frontage road. Boyer provided irrigation and maintenance services until June 2014.

Project Details

Original Construction Cost:
$1,437,954
Final Construction Cost:
$1,437,954
Date of Notice to Proceed:
10/2011
Type of Construction:
Landscape
Original Substantial Completion:
04/2014
Actual Substantial Completion:
04/2012
Final Payment Dates:
06/2014
Project Manager:
Sid Morse
Project Superintendent:
J. Reyes Razo
MEP subcontractors:
Boyer Self Performed
Length of Relationship with Owner:
9 years