SCADA & Communications Systems Phases 1, 2 & 3

Location: Houston, TX
Project Type: Improvements
Owner:
city houston
City of Houston Nat Iyer 713 837-0870
Engineer:
Camp Dresser & McKee Sean Tenney, P.E. 713 850-1921

Project Scope

Boyer provided SCADA System & Communication improvements to the Eastwater Purification plant and ten various groundwater facilities throughout the City of Houston. Boyer also furnished and implemented communications system between the city and various water facilities. The installation of the wireless backbone shown above was accomplished using ten existing water towers located around Houston. The antenna pods were designed, fabricated and installed by Boyer, Inc.

Project Details

Original Construction Cost
$27,778,388
Final Construction Cost
$27,966,511
Date of Notice to Proceed
06/05
Type of Construction
Improvements
Substantial Completion
06/08
Project Manager
Jack Levy/Stacy Jordan
Project Superintendent
Tim Adam/Ryan Divin
Major Subcontractors
Boyer Self Performed