Project Scope
This project involves the comprehensive rehabilitation of 3,275 linear feet (LF) of a century-old storm drain with 3 to 6 feet of cover. Utilizing the Danby Grouted-In-Place-Liner (GIPL) system, the scope includes cleaning, hydro-blasting, rebar installation, and lining followed by 5,000 psi structural grouting. Throughout the process, approximately 100 active service connections will be sequentially tied back into the system. Once complete, this structural restoration will extend the infrastructure's service life by more than 100 years.