Post Oak Blvd. Reconstruction South Package, Richmond Ave. to Westheimer Road
Location: Houston, TX
Project Type: Rehabilitation
Project Type: Rehabilitation
Owner:


Uptown Development Authority (UDA) | Robert Taube | 713.621.2011
GC:
SER Construction Partners, LLC | Joseph Camp, Project Mgr. | 281.408.0528
Engineer:
Gunda Corporation | Shashider Velugati, PE | 713.541.3530
Project Scope
Constructed 2,735 linear feet of CenterPoint Energy 35kV primary duct bank for the dedicated Metro Bus Lane. This scope included a 150-linear-foot, 4’x6’ hand-mined boxwood tunnel under Westheimer Road. Additional deliverables featured manholes, handholes, transformer and switch pads at the proposed bus platforms, and lateral duct banks connecting to existing CenterPoint Energy manholes on Post Oak Blvd.