Post Oak Blvd. Reconstruction Middle Package, Westheimer Road to San Felipe Road

Location: Houston, TX
Project Type: Rehabilitation
Owner:
Uptown Development Authority
Uptown Development Authority (UDA) | Robert Taube | 713.621.2011
GC:
Reytec Construction Resources, Inc. | Keegan Droxler, PM | 832.844.8322
Engineer:
Gunda Corporation | Shashider Velugati, PE | 713.541.3530

Project Scope

 Installed 498-linear-foot CenterPoint Energy 35kV primary duct bank for the dedicated Metro Bus Lane. The project also included installing manholes, handholes, transformer and switch pads at the proposed bus platforms, and lateral duct banks connecting to existing CenterPoint Energy manholes on Post Oak Blvd.

Project Details

Original Construction Cost
$1,005,425
Final Construction Cost
$1,050,125
Date of Notice to Proceed
03/2018
Type of Construction
Rehabilitation
Substantial Completion
04/2019
Project Manager
Barry Buse
Project Superintendent
Emmitt Malmay
Major Subcontractor
Boyer Self Performed