Lift Station Renewal and Replacement @ MacGregor Way North#1, Magnet & Westpark #1

Location: Houston, TX
Project Type: Rehabilitation
Owner:
City of Houston | Boyer Inc has a 40 year relationship with the Owner
General Contractor:
Industrial TX Corp. | Craig Ellington | 713.254.2022
Engineer:
CP&Y | Camille Sowells, PE | 713.532.1730

Project Scope

This project entailed the electrical rehabilitation of three (3) existing Lift Stations:  MacGregor Way North #1, Magnet and Westpark #1 consisting of demolition and removal of the existing electrical and instrumentation systems; installation of new electrical power distribution transformers and switch gear, motor control centers (MCC), high and low voltage panel boards, wiring, conduit, grounding, and area lighting; integration and programming of PLC and SCADA systems; installation and connection of standby and portable generator systems including automatic and manual transfer switches and disconnects. Electrical connections for pumps, motors, mechanical equipment, safety systems, and site facilities. Power system studies and arc flash was performed and implemented necessary electrical modifications, coordinated work to maintain continuous lift station operation. 

Project Details

Original Construction Cost:
$4,244,375
Final Construction Cost:
$5,036,154
Date of Notice to Proceed:
05/2022
Type of Construction:
Rehabilitation
Substantial Completion:
12/2026
Project Manager:
Ryan Divin
Project Superintendent:
Martin Palacios
Major Subcontractor:
Boyer Self Performed