LED Parking Lot Lights at Green Tree, Elm Grove and Timbers Elementary School

Location: Humble, TX
Project Type: New/Expansion
Owner:
Humble ISD
Kenny Kendrick- 281-641-8701

Project Scope

Add Light Poles and upgraded all lighting fixture to LED lamps.

Project Details

Original Construction Cost:
$90,130
Final Construction Cost:
$90,130
Date of Notice to Proceed:
08/12
Type of Construction:
New/Expansion
Substantial Completion:
11/12
Actual Substantial Completion:
11/12
Final Payment Dates:
12/12
Project Managers:
Tim Tyler
Project Superintendent:
John Rossio
Length of Relationship with Owner:
6 years