Lake Houston Pump Station Remote Operations Center

Location: Crosby, TX
Project Type: Rehabilitation
Owner:
San Jacinto River Authority
General Contractor:
Noble Building & Development, LLC | Stan Frey | 979.709.3046
Engineer:
HALFF | Timothy Lott | 214.346.6200

Project Scope

Provided all labor, materials, equipment, and services necessary to complete all electrical work in accordance with project plans and specifications, including power and SCADA duct banks, pull boxes, manholes, and required splicing into existing duct banks. Scope includes grounding and lightning protection; lighting, receptacles, and power circuits for the water well and operations buildings; power circuits and disconnects for the OSSF system; and raceways, cable trays, conduit drops, and pull strings for CCTV and data systems. Assisted with start-up and commissioning, with all work performed per approved plans and specifications. 

Project Details

Original Construction Cost:
$908,765
Final Construction Cost:
$977,576
Date of Notice to Proceed:
02/2023
Type of Construction:
Rehabilitation
Substantial Completion:
08/2024
Project Manager:
Robert Cornwall
Project Superintendent:
John Rossio
Major Subcontractor:
Boyer Self Performed