Lake Houston Pump Station Discharge Piping Rehab

Location: Highlands, TX
Project Type: Rehabilitation
Owner:
sjra
San Jacinto River Authority | Highlands Division | 281.843.3300
Construction Manager:
Texan Construction Solutions, LLC | Ed Maldondo, PM | 713.677.9406
Engineer:
Texas Water Engineering, PLLC | Victoria Foss, PE | 832.865.4979

Project Scope

San Jacinto River Authority’s Lake Houston Pump station site was in need of repairing its main discharge piping. The piping was over 50 years’ old and showing signs of severe corrosion. The pump station could not be entirely shut down during rehab because it is a major component and supplies water to downstream high demand customers. To repair the discharge piping an internal carbon fiber wrap was used to structurally reinforce it, but in order to make this happen a much larger work scope was required. This work scope included installing a new slide gate, grout filled rip-rap, a temporary road crossing, a backup bypass pump system, a carbon fiber structural pipe reinforcement and restore the project site and roads. 

Project Details

Original Construction Cost
$1,441,778
Final Construction Cost
$998,810.00
Date of Notice to Proceed
01/2019
Type of Construction
Rehabilitation
Substantial Completion
04/2019
Project Manager
Ryan Pedersen
Project Superintendent
Juan “Burger” Hernandez, II
Major Subcontractor
Fibrwrap Construction Srvs | Sunbelt Rentals