INEOS New User Pipeline Installation

Location: Bayport Facility, Pasadena, TX
Project Type: New
Owner::
Gulf Coast Authority | Jonte L. Greer, Assistant Director – General Engineering | 281.226.1127
Engineer::
Parsons | Jainil Shah, Sr. Project Manager | 281.714.8434

Project Scope

Constructed approximately 50 feet of 10-inch stainless steel pipeline, including isolation valves, an expansion joint, check valves, foundations and supports, auto-sampler tubing, a flow meter, a transmitter, and associated wiring.

Project Details

Original Construction Cost:
$168,900
Final Construction Cost:
$207,885
Date of Notice to Proceed:
06/2022
Type of Construction:
New
Substantial Completion:
04/2023
Project Manager:
Nathan Davis
Project Superintendent:
Larry Currie
Major Subcontractor:
Boyer Self Performed