Galveston Causeway Area Foundation Rehab 2013

Location: Galveston, TX
Project Type: New/Maintenance
Owner:
CenterPoint Energy Houston Electric, LLC
Alan Valicek 713 945-6626
Engineer of Record:
CenterPoint Energy Houston Electric, LLC

Project Scope

Sandblast, wash and apply two separate coatings of marine silicone paint to the base plates, nuts, bolts and legs of thirteen (13) power transmission structures in Galveston Bay adjacent to the Galveston Causeway.

Project Details

Original Construction Cost:
$146,167
Final Construction Cost:
$126,923
Date of Notice to Proceed:
11/13
Type of Construction:
New/Maintenance
Original Substantial Completion:
11/13
Actual Substantial Completion:
11/13
Final Payment Dates:
12/13
Project Managers:
Daryn Ball
Project Superintendent:
Bruce West
MEP subcontractors:
Boyer Self Performed
Length of Relationship with Owner:
13 years