Ecological Site Assessment

Location: Sabine River, Marathon Phoenix Lake
Project Type: Barge Services
Owner:
Bill Pierce, Project Manager 832 251-5168

Project Scope

Provided barge and two man crew to support Tetra-Tech, Inc. for geoprobe ecological site assessment. The services performed included all labor and equipment for mobilization, barge assembly, barge loading, barge operation and demobilization. The work was performed in the Sabine River, Marathon Phoenix Lake site.

Project Details

Original Construction Cost:
$37,600
Final Construction Cost:
$37,600
Date of Notice to Proceed:
02/15
Type of Construction:
Barge Services
Substantial Completion:
02/15
Project Managers:
Daryn Ball
Project Superintendent:
Bruce West
Major Subcontractors:
Boyer Self Performed