Clinton Drive Emergency Point Repair 60” Force Main

Location: Houston, TX
Project Type: Rehabilitation
Owner:
city houston
City of Houston
Construction Manager:
PM Construction & Rehab, LLC a PURIS Company | Jack Simmons, PMP, Project Manager | 281.714.7048

Project Scope

We closed three lanes of traffic on Clinton Drive to facilitate critical repairs to three separate damaged sections of a 60-inch Hobas force main. The objective was to restore Clinton Drive to its original condition. One repair site was complicated by an active 8-inch CenterPoint gas line situated directly above the damaged pipe; this specific repair required the application of both a fiberglass wrap and a Hobas pressure coupling to ensure integrity and safety. 

Project Details

Original Construction Cost
$1,044,777
Final Construction Cost
$1,044,777
Date of Notice to Proceed
02/2024
Type of Construction
Rehabilitation
Substantial Completion
04/2024
Project Manager
John Tompkins, PE
Project Superintendent(s)
Juan “Burger” Hernandez, II
Major Subcontractor
Boyer Self Performed