City of Galveston Spanish Grant LS #57
Location:
Galveston, TX
Project Type:
New/Expansion
Owner:
City of Galveston
Daniel Christodoss-409-797-3644
Engineer:
LAN Engineering
Bill Schalfer-713-266-6900
Project Scope
Replace and Upgrade Submersible Pumps and Motors, Elevated Platform with Stairs, NEMA 4X Control Panel, and Electrical Components.
Project Details
Original Construction Cost:
$296,799
Final Construction Cost:
$310,294.00
Date of Notice to Proceed:
02/16
Type of Construction:
New/Expansion
Substantial Completion:
06/16
Actual Substantial Completion:
06/16
Final Payment Dates:
07/16
Project Managers:
Gary Wachsmann
Project Superintendent:
Larry Currie
Length of Relationship with Owner:
13 years